Drainage has to be decided before the slab goes down, not during the build — and Cumbrian sites often need an off-mains and site-specific approach.

Last reviewed 2026-09-07

Drainage is one of the few parts of a project that genuinely has to be resolved before construction, not during it. Once foundations and a slab are in, moving a drain run, changing a soakaway location or discovering the ground will not percolate all become expensive, disruptive problems instead of design decisions.

Cumbrian sites are more likely than most to be off-mains for foul drainage, and more likely to sit on ground that does not percolate well, over a watercourse, or with drainage easements crossing neighbouring land. None of this is unusual, but all of it needs establishing early.

This guidance is a framework for the decisions to make, not a substitute for a proper drainage design — that should come from a suitably qualified designer, and any off-mains system needs to meet current environmental and Building Regulations requirements.

Quick answer

Establish whether mains foul drainage is available at the boundary before assuming an off-mains solution is needed, and vice versa.

Do not assume a soakaway will work — get a percolation test done before the design relies on one.

Off-mains foul systems (package treatment plants, septic tanks) generally need environmental permitting or exemption confirmation as well as Building Regulations compliance.

Establishing what already exists

Before any new design is drawn, find out what drainage already serves the site: is there an existing connection, and does it work; where do existing pipe runs cross the plot, and are there any easements or rights allowing a neighbour's drainage to cross the land, or this site's drainage to cross someone else's; and what condition are any existing inspection chambers, septic tanks or soakaways in.

Existing drainage that appears unused is not necessarily disused — it may still be live, and building over or near it without checking is a common and costly mistake.

Foul water — mains or off-mains

Where a mains sewer connection is available, the practical questions are where the connection point is, how deep it runs, who owns and maintains the section between the site and the main, and whether any adoption agreement is needed for new drainage that will eventually be adopted.

Where mains drainage is not available — common on rural Cumbrian plots — the site needs an off-mains solution: typically a septic tank or package sewage treatment plant discharging to a soakaway or, in some cases, a watercourse. What is acceptable depends on the site, the receiving ground or watercourse, and current environmental regulation — a package treatment plant discharging to a watercourse, for example, generally needs to meet specific quality and permitting requirements.

Surface water

Roof and hardstanding water has to go somewhere, and the options are broadly: a soakaway, a watercourse, a surface water sewer, or attenuation with a controlled discharge rate. Which is available and acceptable depends on the ground, the site's flood risk and any discharge restrictions imposed by the planning authority or drainage authority.

  • Percolation testing before any soakaway is assumed to work — a soakaway on poorly draining ground will fail, often expensively, after construction
  • Attenuation, where discharge rates to a sewer or watercourse are restricted by condition or by the receiving system's capacity
  • Separating clean roof water from potentially contaminated yard or farm water, particularly on agricultural sites
  • Land drainage where the surrounding ground stays wet regardless of the building's own drainage
  • Existing drainage running under or near a proposed footprint, and where it needs diverting to

Watercourses, levels and easements

Discharging to, or working near, a watercourse can bring its own consent requirements from the relevant environmental regulator, separate from planning permission. Levels across a site also matter more than they first appear — drainage runs by gravity, and getting falls wrong, or discovering the invert level needed is deeper than assumed, changes excavation depths and cost.

Where drainage needs to cross a neighbouring property, or a neighbour's drainage crosses this site, a formal easement — or the absence of one — is worth establishing before design rather than after a dispute arises.

Building over and future maintenance

Building over or near an existing sewer, even a private one, is generally controlled and may need agreement from the sewer's owner or the water company, particularly if it could later be adopted. Beyond the build itself, inspection chambers need to remain accessible for maintenance for the life of the building — burying a chamber under a patio or driveway creates a maintenance problem that outlasts the original contractor by decades.

Choosing between soakaway, watercourse and attenuation

Surface water disposal in Cumbria usually comes down to a small set of options, and the right one depends on ground, site levels and any restrictions imposed by the planning or drainage authority.

OptionDepends onTypical consideration
SoakawayGround percolation rateNeeds a passed percolation test; fails on clay or high water table
Watercourse dischargeProximity, consent, flood riskMay need consent from the environmental regulator and a controlled rate
Surface water sewerAvailability and capacityConnection point, depth and any capacity restriction from the sewerage undertaker
Attenuation with controlled dischargeSite space for a tank or pondSlows discharge rate to what the receiving system can take
Common surface water disposal options

Off-mains foul systems in practice

Septic tanks discharge to a drainage field or soakaway and rely on the surrounding ground to treat the effluent further, which means they need the same percolation testing as a surface water soakaway, and generally more land around them than a compact package treatment plant. Package treatment plants actively treat the effluent before discharge, which allows discharge to a soakaway or, where permitted, a watercourse, but they need a power supply and periodic servicing that a septic tank does not.

Both need adequate separation from the building, from any water supply (particularly a private well or borehole), and from site boundaries — the exact distances depend on the system and the receiving ground, and should be confirmed with the system manufacturer's guidance and the environmental regulator rather than assumed from a neighbouring property's installation.

Cut-and-fill, levels and why gravity drainage drives excavation depth

Drainage runs by gravity from the highest point that needs draining to the lowest point of discharge, which means the invert level required at the connection or discharge point can set the excavation depth for the whole run, sometimes deeper than groundworks would otherwise need to go. On a sloping site, this interacts directly with cut-and-fill decisions — the final building platform level affects whether drainage can fall to the outfall at a sensible depth, or whether a pumped solution becomes necessary.

Getting a topographic survey done before the drainage strategy is fixed avoids discovering, mid-excavation, that the discharge point is higher than the pipe run needs it to be.

Drainage on agricultural and rural sites

Farm and rural sites often bring extra drainage complexity: yard water that may be contaminated with slurry or fuel and cannot simply join clean roof water, land drains that were installed decades ago and are poorly recorded, and watercourses used for stock or irrigation that any new discharge needs to respect. Separating clean and dirty water at source is usually cheaper and more robust than trying to treat combined water later, and is often expected by the environmental regulator in any case.

What SHS can help with

SHS is the contractor, not the planning authority. What SHS can do is look at the drainage strategy from a build point of view — access, ground conditions, levels, drainage, foundations and buildability — and tell you plainly what the construction side is likely to involve.

If drawings already exist, send them. If they do not, a site visit and a conversation usually establishes what information you need to gather next and who you need it from.

Worth answering before you start

  • Is a mains foul connection available at the boundary, and at what depth?
  • Has a percolation test actually been carried out, or is a soakaway assumed?
  • Where does existing drainage run under or near the site, and is any of it still live?
  • Is discharge to a sewer or watercourse restricted by condition or capacity?
  • Does an off-mains system need an environmental permit or exemption confirmation?
  • Are inspection chambers positioned so they remain accessible after landscaping or paving?

Planning and regulatory requirements vary by property, location and project. SHS provides practical construction guidance but does not replace advice from the relevant planning authority, Building Control, architect, engineer or other qualified professional.

Frequently asked questions

It is not advisable. Soakaways rely on the ground percolating water at a reasonable rate; a percolation test establishes whether that is realistic before the design and cost commit to it.

Have drawings or site photos?

Send them to SHS and we can review the construction side of the project.

Planning and regulatory requirements vary by property, location and project. SHS provides practical construction guidance but does not replace advice from the relevant planning authority, Building Control, architect, engineer or other qualified professional.